The term ‘protected species’ refers to species that are protected by legislation. The Wildlife and Countryside Act and the Natural Environment and Rural Communities Act making it an offence to intentionally, or recklessly kill, injure, or take a protected species, or damage, destroy or obstruct access to structures or places used by protected species for shelter, breeding or protection.
Construction inevitably involves disturbing existing sites and buildings, and this can impact on the ecology. This is true of urban and rural sites, new-build construction, refurbishment projects and demolition, and relates not only to the specific structures being constructed or changed, but also to the land surrounding them. Where this affects protected species or habitats, there can be significant consequences, including delay, expense, suspension of the works, disputes and even prosecutions.
It is important to ensure that protected species are identified as early as possible in the development of a project, when it is still relatively straight forward to accommodate any necessary changes or constraints. The presence of protected species will need to be determined in advance of a planning application for works that may disturb them and this is a material consideration for planning authorities determining applications.
In the first instance, assessments may take the form of a scoping survey (or extended Phase 1 survey) which might include a desk-based study and a site survey. The resulting report should indicate the habitats and species present and their locations, their potential impact, the legal position, and the need for further surveys.
Desk-based studies might be based on information held by the Local Environmental Records Centre (LERC or LRC). For contact details of the relevant LERC see www.alerc.org.uk. The National Biodiversity Network (NBN) Gateway may be a useful source of information, but there are restrictions on use of the data for commercial purposes.
Aspects of the site that might suggest the presence of protected species might include the presence of: traditional timber framed buildings; buildings that are not used frequently; old buildings or farm buildings; large gardens; lakes or water courses; heathland; meadow; parkland; pasture; brownfield land; woodland; scrub; hedgerows; coastal habitats; complex, large or old trees or caves.
If a Phase 2 survey is considered necessary, this should provide sufficient information for detailed assessment of the potential impacts of the development and propose measures to avoid, reduce, mitigate (eg translocation) or compensate (eg biodiversity offsetting) for those impacts.
Natural England have produced a flow chart and decision tree offering guidance on when protected species surveys are likely to be required.
Surveys should be undertaken by suitably experienced specialists. It may be possible to undertake scoping surveys at any time, but detailed surveys may have to be undertaken at certain times. Ref Natural England Optimum Times to Survey Table. If these windows of opportunity are missed, there can be very serious delays to the development.
Surveys may not necessarily be comprehensive and only provide a snapshot of the time when the survey was carried out. The position can change quickly, in particular in relation to the presence of birds.
Protected animal species include.
- Adders
- Badgers.
- Bats.
- Breeding birds.
- Rare birds.
- Common dormice.
- Grass snakes
- Great crested newts.
- Natterjack toads.
- Otters.
- Pine marten.
- Red squirrel.
- Sand lizards.
- Slowworms.
- Smooth snakes.
- Water voles.
- White clawed crayfish.
Protected plants include:
- Creeping Marshwort.
- Early Gentian.
- Fen Orchid.
- Floating-leaved water Plantain.
- Lilarney Fern.
- Lady’s Slipper.
- Slender Naiad.
- Shore Dock.
- Yellow Marsh Saxifrage.
See Joint Nature Conservation Committee for full details.
Failure to protect species can result in fines or imprisonment.
NB: BS 42020:2013, Biodiversity. Code of practice for planning and development, offers a coherent methodology for biodiversity management.
[edit] Related articles on Designing Buildings
- Bats.
- Biodiversity offsetting.
- Ecological Impact Assessment EcIA.
- Ecological network.
- Ecological survey.
- Ecologist.
- Eco-Management and Audit Scheme.
- Endangered species.
- Great crested newt.
- Japanese knotweed.
- Lights Out: Protecting migratory birds from illuminated skyscrapers.
- Preliminary ecological appraisal.
- Priority habitats and species.
- Protected species licence.
- Translocation.
- Tree preservation order.
- Wildlife and Countryside Act.
[edit] External references
- Construction Manager, CPD: Endangered species on site, 2 September 2013.
- Natural England, Planning FAQ’s.
- CIRIA, DTI, Biodiversity indicators for construction projects. 2003.
- BS 42020:2013, Biodiversity. Code of practice for planning and development.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.